
How Long Does a Planning Application Take?
Understand the real planning timescale before you book builders or start work
Most homeowners want a simple answer: how long will the planning application take?
​
For many domestic projects, the usual answer is around 8 weeks from validation, but the real timescale can be longer once you include:
​
-
Preparing drawings
-
Checking planning constraints
-
Submitting the application
-
Council validation
-
Neighbour consultation
-
Planning officer review
-
Possible amendments
-
The final decision notice
-
Any planning conditions that must be dealt with afterwards
​
GOV.UK says most planning applications are decided within 8 weeks, while unusually large or complex applications in England usually have a 13-week time limit. The Planning Portal also explains that the formal decision period begins after the application has been validated.
​
​
The quick answer
A straightforward householder planning application usually takes:
​
-
1 to 3 weeks to prepare drawings and application information
-
1 to 3 weeks for council validation, depending on the local authority
-
8 weeks for the formal decision period after validation
-
Longer if the council requests changes, extra information or an extension of time
​
So in practical terms, many homeowners should allow around:
​
-
10 to 14 weeks from starting drawings to receiving a decision
-
Longer for complex sites, conservation areas, listed buildings or change of use projects
-
Longer again if structural, building regulations or party wall matters are also needed
​
IMPORTANT POINT
The 8-week period usually starts when the council validates the application, not necessarily the day you submit it.
​
​
Typical planning application timescales
For many homeowner projects, the usual council decision periods are:
​
-
Householder planning applications: around 8 weeks
-
Minor applications: around 8 weeks
-
Major applications: often 13 weeks
-
Some complex or specialist applications: may take longer
-
Applications with Environmental Impact Assessment: may have longer timescales
-
Applications with amendments: may need extra time
-
Applications going to committee: may take longer than delegated decisions
​
Most domestic extensions, loft alterations, garage conversions and smaller homeowner applications are usually treated as householder or minor applications, but the exact route depends on the proposal.
​
​
The planning application timeline:
1. Initial planning review
Before drawings are prepared, it is sensible to check:
​
-
Whether planning permission is needed
-
Whether permitted development may apply
-
Whether a Lawful Development Certificate would be better
-
Whether the property is listed
-
Whether the site is in a conservation area
-
Whether there are Article 4 restrictions
-
Whether previous extensions affect the proposal
-
Whether the project may need building regulations as well
​
This stage can often save time because it helps avoid submitting the wrong type of application.
​
​
2. Preparing the drawings
Most planning applications need clear drawings.
​
These may include:
​
-
Site location plan
-
Block plan
-
Existing floor plans
-
Proposed floor plans
-
Existing elevations
-
Proposed elevations
-
Roof plans where needed
-
Sections where needed
-
Design notes or supporting statements where required
​
The preparation time depends on:
​
-
Whether a measured survey is needed
-
Whether existing drawings are available
-
The size of the property
-
The complexity of the proposal
-
How quickly the design can be agreed
-
Whether supporting reports are required
​
For a simple domestic project, drawings may be prepared quickly. For larger or more complicated projects, this stage can take longer.
​
​
3. Submitting the application
Once the drawings and information are ready, the application can usually be submitted online.
​
The submission may include:
​
-
Application form
-
Ownership certificate
-
Site location plan
-
Existing and proposed drawings
-
Supporting statement if needed
-
Planning fee
-
Any specialist documents requested by the council
​
A good submission reduces the risk of validation delays.
​
​
4. Council validation
Validation is the council’s initial check that the application contains the required information.
​
The council may check:
​
-
Whether the correct application type has been used
-
Whether the right plans have been submitted
-
Whether the drawings are clear
-
Whether the site plan is acceptable
-
Whether the fee is correct
-
Whether ownership certificates are completed
-
Whether extra documents are required
​
If something is missing, the council can make the application invalid and request further information.
​
​
TOP TIP
Validation delays are common. A planning application may be submitted on Monday, but the 8-week decision period may not start until the council confirms it is valid.
​
​
5. Neighbour consultation
Once validated, most planning applications go through consultation.
​
This may involve:
​
-
Letters to neighbouring properties
-
Site notices in some cases
-
Conservation or heritage consultation
-
Highways consultation
-
Tree officer consultation
-
Drainage or environmental consultation
-
Internal council department comments
​
For many householder applications, the neighbour consultation period is often one of the main parts of the 8-week decision process.
​
​
6. Planning officer assessment
The planning officer will usually consider:
​
-
Local planning policy
-
Design and appearance
-
Scale and massing
-
Impact on neighbours
-
Privacy and overlooking
-
Daylight and outlook
-
Parking and access
-
Conservation area impact
-
Heritage issues
-
Trees and landscape
-
Planning history
-
Consultation responses
​
The officer may approve the application, refuse it, or request changes before making a decision.
​
​
7. Amendments and extra information
Applications can take longer if the council asks for changes.
​
This may happen where:
​
-
The design is considered too large
-
The roof form needs adjustment
-
Windows create overlooking concerns
-
Materials need clarification
-
Parking information is missing
-
Heritage issues need more explanation
-
Neighbours have objected
-
The officer wants revised drawings
​
Sometimes amendments are helpful because they can avoid a refusal, but they can also extend the overall timescale.
​
​
8. Decision notice
At the end of the process, the council issues a decision notice.
​
This will normally confirm whether the application is:
​
-
Approved
-
Approved with conditions
-
Refused
-
Withdrawn before decision
​
If approved, the decision notice may include conditions that must be followed.
​
These can relate to:
​
-
Materials
-
Construction hours
-
Privacy screens
-
Obscure glazing
-
Landscaping
-
Drainage
-
Parking
-
Details to be submitted before work starts
​
​
Why planning applications get delayed
Planning applications are often delayed because of:
​
-
Missing drawings
-
Incorrect application type
-
Wrong fee
-
Invalid location plan
-
Incomplete ownership certificate
-
Poorly prepared existing or proposed plans
-
Conservation area issues
-
Listed building issues
-
Highways questions
-
Tree protection concerns
-
Neighbour objections
-
Officer workload
-
Requested design amendments
-
Planning committee dates
-
Extensions of time requested by the council
​
A well-prepared application cannot guarantee a fast decision, but it can reduce avoidable delays.
​
​
Does a planning application always take 8 weeks?
No.
​
The 8-week period is the standard target for many smaller applications, but not every application is decided within exactly 8 weeks.
​
A decision may take longer if:
​
-
The council has a backlog
-
The application is complex
-
The site has planning constraints
-
Extra consultation is needed
-
Amendments are requested
-
The application goes to committee
-
A legal agreement is required
-
The applicant agrees to an extension of time
​
The Planning Portal says most applications are decided within 8 weeks unless they are unusually large or complex, in which case the time limit is extended to 13 weeks.
​
​
Can you speed up a planning application?
You cannot force the council to decide faster, but you can reduce avoidable delays.
​
The best ways to help the application run smoothly are:
​
-
Check the correct planning route before applying
-
Submit accurate drawings
-
Use the correct application form
-
Include the right certificates
-
Pay the correct fee
-
Include a clear description of development
-
Address obvious planning issues early
-
Consider neighbour impact before submission
-
Respond quickly if the council asks for information
-
Avoid changing the design halfway through the process
​
For some complex projects, a paid planning consultancy review before submission can save time by identifying risk early.
​
​
What if the council misses the decision deadline?
If the council does not issue a decision within the statutory period, the applicant may have options.
​
These can include:
​
-
Agreeing an extension of time
-
Waiting for the council decision
-
Chasing the planning officer
-
Escalating the matter within the planning department
-
Appealing for non-determination in appropriate cases
​
The Planning Portal explains that an appeal can be made if the local authority does not issue a decision within 8 weeks, unless the applicant has agreed in writing to extend the period.
​
In practice, many homeowners choose to wait a little longer if the officer is actively working towards a decision, especially where an appeal would take much longer.
​
​
How long should homeowners allow in real life?
For a typical domestic project, a sensible working allowance is:
​
-
2 to 4 weeks for advice, survey, design and drawings
-
1 to 3 weeks for validation
-
8 weeks for council assessment
-
1 to 2 weeks for any final decision notice, conditions or follow-up
​
So a realistic planning stage can often be:
​
-
Around 10 to 14 weeks for a straightforward householder application
-
Around 12 to 18 weeks where validation or amendments are slow
-
Several months for more complex projects, listed buildings, conservation areas or change of use
​
This is why it is usually risky to book builders before the planning position is clear.
​
​
Planning approval is not the end of the process
Even after planning permission is approved, you may still need:
​
-
Building regulations drawings
-
Structural calculations
-
Building control approval
-
Party wall notices
-
Thames Water or sewer build-over approval where relevant
-
Freeholder or leaseholder consent
-
Contractor pricing
-
Construction drawings
-
Discharge of planning conditions
​
Planning permission deals with whether the development is acceptable in planning terms. It does not confirm that the work is structurally designed, buildable or compliant with building regulations.
​
​
IMPORTANT POINT
Do not treat planning approval as permission to start building unless all other required approvals and conditions have also been checked.
​
​
How PAS can help
Planning Application Services (PAS) can help homeowners prepare properly before submitting a planning application.
​
We can help with:
​
-
Initial planning advice
-
Checking whether planning permission is needed
-
Reviewing permitted development options
-
Advising on Lawful Development Certificates
-
Preparing planning drawings
-
Preparing supporting information
-
Submitting planning applications
-
Responding to validation requests
-
Advising on amendments
-
Helping you understand planning conditions
-
Coordinating building regulations, structural and party wall support where needed
​
The aim is to reduce avoidable delays and help you take the correct route from the start.
​
​
When paid planning consultancy is useful
Paid planning consultancy is useful where you need a proper desktop review before spending money on a full application.
​
It can help where:
​
-
You are unsure whether planning permission is required
-
You need a faster view than waiting for council pre-application advice
-
The project is in a conservation area
-
The property is listed or near listed buildings
-
You are considering a change of use
-
You want to convert a property
-
You are planning a new build
-
You are dealing with an HMO or Airbnb proposal
-
You have had a previous refusal
-
You want to understand the likely planning route before instructing drawings
​
PAS can usually give a practical view much earlier than the formal council decision process.
​
​
Need to know how long your planning application may take?
If you are asking “How long does a planning application take?”, the best next step is to look at the actual project, not just the general timescale.
​
The answer depends on:
​
-
The type of application
-
The property
-
The planning history
-
The quality of the drawings
-
The local authority
-
Whether consultation issues are likely
-
Whether amendments may be needed
-
Whether other approvals are involved
​
A clear planning review at the beginning can help you avoid wasted time later.
​
​
Next Steps:
​
Tell Us What You Need
Use our enquiry form to tell PAS about your property and the work you are considering.
​
We can help you understand:
​
-
Whether planning permission is needed
-
What type of application may be required
-
How long the process is likely to take
-
Whether permitted development or an LDC may be better
-
What drawings or documents may be needed
​
​
Planning Consultancy
Choose paid planning consultancy if you need a proper desktop review before committing to drawings, builders or applications.
​
This is useful for:
​
-
Extensions
-
Loft conversions
-
Garage conversions
-
New builds
-
HMOs
-
Airbnb use
-
Property conversions
-
Conservation area projects
-
Complex or uncertain planning issues
​
​
Plans and Drawings
If your project needs drawings, PAS can prepare clear planning drawings to support the application and reduce validation problems.
​
​
Planning Applications
If planning permission is required, PAS can help prepare and submit the application and guide you through the council process.
​
​
