top of page
planning_application_services_932100005.jpg

How Long Does a Planning Application Take?

Understand the real planning timescale before you book builders or start work

Most homeowners want a simple answer: how long will the planning application take?

​

For many domestic projects, the usual answer is around 8 weeks from validation, but the real timescale can be longer once you include:

​

  • Preparing drawings

  • Checking planning constraints

  • Submitting the application

  • Council validation

  • Neighbour consultation

  • Planning officer review

  • Possible amendments

  • The final decision notice

  • Any planning conditions that must be dealt with afterwards

​

GOV.UK says most planning applications are decided within 8 weeks, while unusually large or complex applications in England usually have a 13-week time limit. The Planning Portal also explains that the formal decision period begins after the application has been validated.

​

​

The quick answer

 

A straightforward householder planning application usually takes:

​

  • 1 to 3 weeks to prepare drawings and application information

  • 1 to 3 weeks for council validation, depending on the local authority

  • 8 weeks for the formal decision period after validation

  • Longer if the council requests changes, extra information or an extension of time

​

So in practical terms, many homeowners should allow around:

​

  • 10 to 14 weeks from starting drawings to receiving a decision

  • Longer for complex sites, conservation areas, listed buildings or change of use projects

  • Longer again if structural, building regulations or party wall matters are also needed

​

IMPORTANT POINT
The 8-week period usually starts when the council validates the application, not necessarily the day you submit it.

​

​

Typical planning application timescales

 

For many homeowner projects, the usual council decision periods are:

​

  • Householder planning applications: around 8 weeks

  • Minor applications: around 8 weeks

  • Major applications: often 13 weeks

  • Some complex or specialist applications: may take longer

  • Applications with Environmental Impact Assessment: may have longer timescales

  • Applications with amendments: may need extra time

  • Applications going to committee: may take longer than delegated decisions

​

Most domestic extensions, loft alterations, garage conversions and smaller homeowner applications are usually treated as householder or minor applications, but the exact route depends on the proposal.

​

​

The planning application timeline:

 
1. Initial planning review

Before drawings are prepared, it is sensible to check:

​

  • Whether planning permission is needed

  • Whether permitted development may apply

  • Whether a Lawful Development Certificate would be better

  • Whether the property is listed

  • Whether the site is in a conservation area

  • Whether there are Article 4 restrictions

  • Whether previous extensions affect the proposal

  • Whether the project may need building regulations as well

​

This stage can often save time because it helps avoid submitting the wrong type of application.

​

​

2. Preparing the drawings

Most planning applications need clear drawings.

​

These may include:

​

  • Site location plan

  • Block plan

  • Existing floor plans

  • Proposed floor plans

  • Existing elevations

  • Proposed elevations

  • Roof plans where needed

  • Sections where needed

  • Design notes or supporting statements where required

​

The preparation time depends on:

​

  • Whether a measured survey is needed

  • Whether existing drawings are available

  • The size of the property

  • The complexity of the proposal

  • How quickly the design can be agreed

  • Whether supporting reports are required

​

For a simple domestic project, drawings may be prepared quickly. For larger or more complicated projects, this stage can take longer.

​

​

3. Submitting the application

Once the drawings and information are ready, the application can usually be submitted online.

​

The submission may include:

​

  • Application form

  • Ownership certificate

  • Site location plan

  • Existing and proposed drawings

  • Supporting statement if needed

  • Planning fee

  • Any specialist documents requested by the council

​

A good submission reduces the risk of validation delays.

​

​

4. Council validation

Validation is the council’s initial check that the application contains the required information.

​

The council may check:

​

  • Whether the correct application type has been used

  • Whether the right plans have been submitted

  • Whether the drawings are clear

  • Whether the site plan is acceptable

  • Whether the fee is correct

  • Whether ownership certificates are completed

  • Whether extra documents are required

​

If something is missing, the council can make the application invalid and request further information.

​

​

TOP TIP
Validation delays are common. A planning application may be submitted on Monday, but the 8-week decision period may not start until the council confirms it is valid.

​

​

5. Neighbour consultation

Once validated, most planning applications go through consultation.

​

This may involve:

​

  • Letters to neighbouring properties

  • Site notices in some cases

  • Conservation or heritage consultation

  • Highways consultation

  • Tree officer consultation

  • Drainage or environmental consultation

  • Internal council department comments

​

For many householder applications, the neighbour consultation period is often one of the main parts of the 8-week decision process.

​

​

6. Planning officer assessment

The planning officer will usually consider:

​

  • Local planning policy

  • Design and appearance

  • Scale and massing

  • Impact on neighbours

  • Privacy and overlooking

  • Daylight and outlook

  • Parking and access

  • Conservation area impact

  • Heritage issues

  • Trees and landscape

  • Planning history

  • Consultation responses

​

The officer may approve the application, refuse it, or request changes before making a decision.

​

​

7. Amendments and extra information

Applications can take longer if the council asks for changes.

​

This may happen where:

​

  • The design is considered too large

  • The roof form needs adjustment

  • Windows create overlooking concerns

  • Materials need clarification

  • Parking information is missing

  • Heritage issues need more explanation

  • Neighbours have objected

  • The officer wants revised drawings

​

Sometimes amendments are helpful because they can avoid a refusal, but they can also extend the overall timescale.

​

​

8. Decision notice

At the end of the process, the council issues a decision notice.

​

This will normally confirm whether the application is:

​

  • Approved

  • Approved with conditions

  • Refused

  • Withdrawn before decision

​

If approved, the decision notice may include conditions that must be followed.

​

These can relate to:

​

  • Materials

  • Construction hours

  • Privacy screens

  • Obscure glazing

  • Landscaping

  • Drainage

  • Parking

  • Details to be submitted before work starts

​

​

Why planning applications get delayed

 

Planning applications are often delayed because of:

​

  • Missing drawings

  • Incorrect application type

  • Wrong fee

  • Invalid location plan

  • Incomplete ownership certificate

  • Poorly prepared existing or proposed plans

  • Conservation area issues

  • Listed building issues

  • Highways questions

  • Tree protection concerns

  • Neighbour objections

  • Officer workload

  • Requested design amendments

  • Planning committee dates

  • Extensions of time requested by the council

​

A well-prepared application cannot guarantee a fast decision, but it can reduce avoidable delays.

​

​

Does a planning application always take 8 weeks?

 

No.

​

The 8-week period is the standard target for many smaller applications, but not every application is decided within exactly 8 weeks.

​

A decision may take longer if:

​

  • The council has a backlog

  • The application is complex

  • The site has planning constraints

  • Extra consultation is needed

  • Amendments are requested

  • The application goes to committee

  • A legal agreement is required

  • The applicant agrees to an extension of time

​

The Planning Portal says most applications are decided within 8 weeks unless they are unusually large or complex, in which case the time limit is extended to 13 weeks.

​

​

Can you speed up a planning application?

 

You cannot force the council to decide faster, but you can reduce avoidable delays.

​

The best ways to help the application run smoothly are:

​

  • Check the correct planning route before applying

  • Submit accurate drawings

  • Use the correct application form

  • Include the right certificates

  • Pay the correct fee

  • Include a clear description of development

  • Address obvious planning issues early

  • Consider neighbour impact before submission

  • Respond quickly if the council asks for information

  • Avoid changing the design halfway through the process

​

For some complex projects, a paid planning consultancy review before submission can save time by identifying risk early.

​

​

What if the council misses the decision deadline?

 

If the council does not issue a decision within the statutory period, the applicant may have options.

​

These can include:

​

  • Agreeing an extension of time

  • Waiting for the council decision

  • Chasing the planning officer

  • Escalating the matter within the planning department

  • Appealing for non-determination in appropriate cases

​

The Planning Portal explains that an appeal can be made if the local authority does not issue a decision within 8 weeks, unless the applicant has agreed in writing to extend the period.

​

In practice, many homeowners choose to wait a little longer if the officer is actively working towards a decision, especially where an appeal would take much longer.

​

​

How long should homeowners allow in real life?

 

For a typical domestic project, a sensible working allowance is:

​

  • 2 to 4 weeks for advice, survey, design and drawings

  • 1 to 3 weeks for validation

  • 8 weeks for council assessment

  • 1 to 2 weeks for any final decision notice, conditions or follow-up

​

So a realistic planning stage can often be:

​

  • Around 10 to 14 weeks for a straightforward householder application

  • Around 12 to 18 weeks where validation or amendments are slow

  • Several months for more complex projects, listed buildings, conservation areas or change of use

​

This is why it is usually risky to book builders before the planning position is clear.

​

​

Planning approval is not the end of the process

 

Even after planning permission is approved, you may still need:

​

  • Building regulations drawings

  • Structural calculations

  • Building control approval

  • Party wall notices

  • Thames Water or sewer build-over approval where relevant

  • Freeholder or leaseholder consent

  • Contractor pricing

  • Construction drawings

  • Discharge of planning conditions

​

Planning permission deals with whether the development is acceptable in planning terms. It does not confirm that the work is structurally designed, buildable or compliant with building regulations.

​

​

IMPORTANT POINT
Do not treat planning approval as permission to start building unless all other required approvals and conditions have also been checked.

​

​

How PAS can help

 

Planning Application Services (PAS) can help homeowners prepare properly before submitting a planning application.

​

We can help with:

​

  • Initial planning advice

  • Checking whether planning permission is needed

  • Reviewing permitted development options

  • Advising on Lawful Development Certificates

  • Preparing planning drawings

  • Preparing supporting information

  • Submitting planning applications

  • Responding to validation requests

  • Advising on amendments

  • Helping you understand planning conditions

  • Coordinating building regulations, structural and party wall support where needed

​

The aim is to reduce avoidable delays and help you take the correct route from the start.

​

​

When paid planning consultancy is useful

 

Paid planning consultancy is useful where you need a proper desktop review before spending money on a full application.

​

It can help where:

​

  • You are unsure whether planning permission is required

  • You need a faster view than waiting for council pre-application advice

  • The project is in a conservation area

  • The property is listed or near listed buildings

  • You are considering a change of use

  • You want to convert a property

  • You are planning a new build

  • You are dealing with an HMO or Airbnb proposal

  • You have had a previous refusal

  • You want to understand the likely planning route before instructing drawings

​

PAS can usually give a practical view much earlier than the formal council decision process.

​

​

Need to know how long your planning application may take?

 

If you are asking “How long does a planning application take?”, the best next step is to look at the actual project, not just the general timescale.

​

The answer depends on:

​

  • The type of application

  • The property

  • The planning history

  • The quality of the drawings

  • The local authority

  • Whether consultation issues are likely

  • Whether amendments may be needed

  • Whether other approvals are involved

​

A clear planning review at the beginning can help you avoid wasted time later.

​

​

Next Steps:

​

Tell Us What You Need

Use our enquiry form to tell PAS about your property and the work you are considering.

​

We can help you understand:

​

  • Whether planning permission is needed

  • What type of application may be required

  • How long the process is likely to take

  • Whether permitted development or an LDC may be better

  • What drawings or documents may be needed

​

​

Planning Consultancy

Choose paid planning consultancy if you need a proper desktop review before committing to drawings, builders or applications.

​

This is useful for:

​

  • Extensions

  • Loft conversions

  • Garage conversions

  • New builds

  • HMOs

  • Airbnb use

  • Property conversions

  • Conservation area projects

  • Complex or uncertain planning issues

​

​

Plans and Drawings

If your project needs drawings, PAS can prepare clear planning drawings to support the application and reduce validation problems.

​

​

Planning Applications

If planning permission is required, PAS can help prepare and submit the application and guide you through the council process.

​

​

planning_application_services.png

Contact Us:

 

Planning Application Services (PAS)
167–169 Great Portland Street
London
W1W 5PF

Tel: 0370 042 2021
Email: help@pasguide.co.uk

Planning Application Types:

 

Pre-Planning Advice
House Extensions
Loft Conversions
Garage Conversions
Garden Buildings
Lawful Development Certificates
Retrospective Planning
View All Application Types

Planning Support:

 

Tell Us About Your Project
Planning Application Help
Fixed-Fee Planning Support
Nationwide Planning Service

Planing Guides

 

Do I Need Planning Permission?
Planning Permission or Permitted Development?
What Is a Lawful Development Certificate?
What Is Retrospective Planning Permission?
How Long Does a Planning Application Take?
What Drawings Do I Need for a Planning Application?How Much Does a Planning Application Cost?
Common Reasons Planning Applications Are Refused
Planning Conditions Explained
What Happens After Planning Approval?

Company / Legal:

 

About PAS
Contact PAS
Privacy Policy
Terms
Cookie Policy

Planning Application Services (PAS) is part of the APN Home Group. © 2026 APN Home Limited. PAS is a trading style of APN Home Limited

bottom of page